Cernavodă nuclear Unit 2 back on Romania’s grid; Unit 1 restart pushed back a day
Unit 2 of Romania’s only nuclear power plant reconnected to the national grid on Wednesday after nearly three months offline because of drought. Operator Nuclearelectrica delayed the return of Unit 1 by one day, to Friday, after it was disconnected on Monday because of a fault outside the nuclear part of the plant.

BUCHAREST, 11 November 2026 – Unit 2 of the Cernavodă nuclear power plant reconnected to Romania’s national power grid on Wednesday and is expected to reach nominal power on Thursday, 12 November, state-controlled operator Nuclearelectrica said. Unit 1 will now return a day later than planned.
Nuclearelectrica first said on Wednesday that Unit 1 would be reconnected on 12 November and reach nominal power on 13 November. In a second filing to the Bucharest Stock Exchange later the same day, it moved reconnection to 13 November and full power to 14 November. The company said the remaining repair work needed more time and was being carried out under nuclear-safety rules, with no impact on staff or the environment.
The Ministry of Energy said Unit 2 had been synchronised with the grid and was resuming electricity deliveries. Its output was still rising when the government’s energy task force met on Wednesday.
Both of the plant’s reactors, which have about 700 MW of installed capacity each according to Ziarul Financiar and Digi24, were taken offline this summer because of low water levels on the Danube, which the plant relies on.
According to Nuclearelectrica’s stock exchange filings, Unit 1 was shut in a controlled way on the morning of 28 July because of a very low level of the river caused by severe drought, a level the company described as unprecedented. Unit 2 began shutting down on the morning of 13 August as the river level kept falling. The company said keeping both units in a safe shutdown state had no impact on nuclear safety.
Unit 1 was resynchronised with the grid on the afternoon of 6 November. It was disconnected again on the evening of 9 November because of a fault in the “classical”, or non-nuclear, part of the unit, Nuclearelectrica said. The company said the fault had no impact on nuclear safety. It added that the plant’s technical director would be replaced from 1 December and that the root cause would be set out in a later report.
Energy Minister Dumitru Chisăliță said on Tuesday that the problem was with the steam turbine, not the reactor, Digi24 and Știrile ProTV reported, the latter citing AGERPRES. Data from grid operator Transelectrica, cited by Antena 3 CNN, Adevărul and România TV, pointed to a failure of the vacuum control system at the turbine condenser, which Mediafax also reported. Nuclearelectrica’s stock exchange filings refer only to a fault in the classical part of the unit and have not specified the component.
On Tuesday, Nuclearelectrica had estimated that repairs to Unit 1 would take two to four days, followed by restart and synchronisation procedures.
Nuclearelectrica says that with both units at nominal power the plant covers about 20% of Romania’s electricity consumption. The return of both units comes as the energy task force prepares the system for winter. On Wednesday it reviewed peak-hour demand forecasts and readiness for the cold season.
Under the revised schedule, Unit 2 should reach full power on Thursday, and Unit 1 should be reconnected on Friday and reach nominal power on Saturday, 14 November. Nuclearelectrica, which is listed on the Bucharest Stock Exchange, has said it will report any further changes to the market.